Uriah Gas Treating and Processing Plant

Constructed during the 2nd quarter of 2011, the Uriah Gas Plant was placed into operation 79 days following contract execution.  Designed, built, owned and operated by GPI, this facility has sustained in excess of 99% runtime.  Rich casinghead gas containing up to 20 PPM of H2S is delivered to the plant at 650 PSIG.  The H2S is removed using a two (2) tower SulfaTreat Unit, the gas is then processed to recover a truckable C2+ NGL product and the pipeline quality residue gas stream is delivered directly into the local distribution system of a large natural gas utility company.  Plans are currently underway to expand the capacity of this facility to handle additional gas from wells that will be developed in the 2nd quarter of 2012.